PHASE 1
Phase I is a stand-alone building located at 1101 Connecticut Street. Phase I ground-breaking occurred in 2017 with expected completion in December 2018 and ready for occupancy in January 2019.
PHASE 2
Phase 2 demolition (RED) is estimated to occur in 2019. Projected completion is 2021
PHASE 3
Phase 3 demolition (RED) is estimated to occur in 2022. Projected completion is 2024.
PHASE 4
Phase 4 demolition (RED) is estimated to occur in 2024. Projected completion is 2026.
PHASE 5
Phase 5 demolition (RED) is estimated to occur in 2026. Projected completion is 2029.